How a plastic heat staking cell is specified: stud diameter and material, stake temperature and hold time, positioning jig and clamp, and what the joint…

How a hot riveting cell is specified

Hot riveting, or heat staking, forms a plastic stud over a metal or plastic part to hold the stack together without a separate fastener. The specification starts from the stud: diameter, height and the plastic grade, since nylon, PP, ABS and PC each melt and flow at a different temperature window. The joint stack, the head shape the stake has to form, and any nearby painted or textured surface decide the heater head size, the clamp fixture and the servo or cylinder drive. Precision positioning jigs and hardened steel clamp molds keep the part flat while the stud forms.

Station sequence

The parts stack into the positioning jig and the clamp holds them flat, the heated stake head descends onto the stud, the tip melts and forms the stud into the required head, and the joint holds through a set cooling time before the head lifts and the part unloads. Servo or cylinder travel controls the stake depth; temperature is held stable cycle to cycle. Dedicated fixtures carry auto interior parts such as instrument panels, where part position and surface finish matter most.

What decides reject rate

  • Temperature window. Too hot burns or shrinks the stud and marks the surrounding surface; too cold leaves a weak stake that pulls off under load.
  • Hold and cool time. Releasing before the head sets deforms the still-soft stake and loses the head shape.
  • Stud variation. A short or over-size stud does not form the same head, so one recipe does not hold across stud batches.
  • Fixture alignment. A part that lifts or tilts under clamp force stakes off-center, which shows as a loose edge rather than a visible fault.
  • Surface protection. The heater head or clamp that contacts a textured or painted face can scuff it unless the jig shields the surface.

What we need from you

  • Part and stud drawings: plastic grade, stud diameter and height, and the required head shape
  • The joint stack and any surface finish or nearby insert the head must not touch
  • Target cycle time, annual volume and the part numbers sharing the cell
  • Any joint check you require: stake height, pull-off force or appearance inspection

How the project runs

Quote from drawing, heater head and clamp fixture design, build, then run-off with your own mouldings in our plant in Chashan, Dongguan. The temperature profile, stake depth and acceptance test are agreed before tooling is cut. Two-year warranty, with operator training at run-off.

Send a drawing to [email protected] or call +86-18123647785. Related lines: ultrasonic plastic welding machines, automatic riveting machines.

Machines for this part: Hot riveting machine — the models we build, with station count and cycle time per line.

Quotation

Send the drawing for this line. We come back with station layout, cycle time and price.

A quote normally takes three working days once the part information is complete. If something is missing we tell you which drawing is needed instead of guessing a price.

  • 012D drawing or STEP file, and the sub-parts
  • 02Material and surface finish of each component
  • 03Target cycle time, annual volume, shifts per day
  • 04The defect you cannot ship — leak, torque, appearance